Construction of Batken-Kara-Bak road ongoing

AKIPRESS.COM - Construction of Batken-Kara-Bak road is ongoing.

This road is around 7 km long. Construction started in April. Up to date, 3.5 km of the road were built.

30 million som was allocated for construction of the road. Another 25 million som is needed to finish construction of the road.

The given road is section of Osh-Batken-Razzakov bypass road.

The population of the town of Batken exceeds 30,000 people. The populatio of Kara-Bak rural municipality passes 20,000 people.

All rights reserved

© AKIpress News Agency - 2001-2024.

Republication of any material is prohibited without a written agreement with AKIpress News Agency.

Any citation must be accompanied by a hyperlink to akipress.com.

Our address:

299/5 Chingiz Aitmatov Prosp., Bishkek, the Kyrgyz Republic

e-mail: english@akipress.org, akipressenglish@gmail.com;

Follow us:

Log in


Forgot your password? - recover

Not registered yet? - sign-up

Sign-up

I have an account - log in

Password recovery

I have an account - log in